Discovery in the Area where Solar Energy will be installed and the Importance of Discovery
If you want to benefit from solar energy much more efficiently, the first thing to do is to get help from a professional team. In fact, the most important stage to be done before the system is installed is the discovery stage. Because if this stage is done at the beginning of the project, more clear and solid results will be obtained. Information from the first discovery, measurements, etc. It will provide great convenience in solar energy installation project. The discovery phase is a very important issue in seeing the area where the SPP will be installed closely and establishing the power plant properly, applicable and as a whole from the beginning. Of course, more detailed explorations should be made in the later stages of the project.
First of all, the suitability of your land for installing a GES should be checked. In order to see the suitability of your roof and to use its potential efficiently, your roof should be explored. A good inspection ensures a more accurate installation by minimizing errors. For example, it will prevent planning errors and erroneous calculations.
The importance of discovery is very important for the settlement, projecting and installation stages to be more accurate and applicable. According to the results of the discovery, it is aimed to establish the cost with the system design, layout plan and other important analyzes for the SPP installation.
In the place where the GES will be installed, the infrastructure should be examined statically and electrically. It is important for the incoming team to take videos and photos, and necessary items such as meters and compass should be kept. All preparations should be made before going exploring and no materials should be forgotten, as you will generally be working outside. What should be in the discovery file should be prepared with the discovery and put in the file. This process will provide a lot of convenience to the company, employees and you in the next stages.

   

Static Inspection Details While Installing SPP;
- Roof dimensions should be measured in width and height.
-The roof covering should be examined in detail and measurements should be made for the materials to be used.
-The width, length and height of the chimney on the roof should be measured. The reason for this is that the shadow made by the chimney is very important in terms of placement and efficiency.
- If there are lighting or ventilation gaps on the roof, these should be measured.
- If there is a parapet on the roof, its height should be measured. The reason for this is that the shadow made by the parapet is important in terms of efficiency.
- If the area where the SPP will be installed is an area exposed to excessive wind, this should be written in the exploration report. Because this should be considered when buying panel holders.
-Measurement of manholes and ridge tops on the roof should be taken.

Manhole: Chimneys established for purposes such as control, intervention, ventilation, connection and return in collector-carrier stormwater and sewer lines are called Inspection Chimney (manhole).

Ridge: It is the uppermost limit of the roof and also the intersection where the roof surfaces rising from the two eaves intersect along a horizontal line.
The shape of the roof, the size of the roof, the coating of the roof and the roof carrier are very important in terms of static and during the projecting phase. Roof covering can be sandwich panel, trapezoidal and membrane. Steel and reinforced concrete can be used in the carrier system.

Electrical Inspection Details While Installing GES;
There are details such as transformer type, transformer power, main switch value, determination of cables. If the transformer power is insufficient, they may suggest you to increase the transformer power and record this in the report. The main switch value is very important for the connection system during the installation phase of the SPP. In addition, if the value of the auxiliary switch is suitable for the system, it should be added to the discovery report. Width and length should be determined and added to the report for cable identification and best system design. If there is a generator in the system, the room should be examined and added to the exploration report.
One of the most important tasks to be done during the exploration before the installation of the SPP is to determine the location of the inverters. It is very important for the inverters to be close to the panel for practicability and to be placed on the north-facing side of the plant due to efficiency and heat.
After the discovery is over, the discovery report is delivered to the authorities, and the next process is the proposal stage. If it is agreed in the proposal for the installation of the facility given to you, the last stage is the installation stage.